Ms. Mustac provided a summary of the Road Rationalization study, project phases and current status. She noted that there have been some added work that had not been included in the initial contract and discussed the recommendation for Council to consider.
Discussion took place with regard to the project technical team and the project phases and timeline as they both have evolved over the course of discussions and review.
Mr. Maisonville noted that due to the nature of the project and the implications that the results may have on municipal budget planning, it would be necessary to commit the time to assessing the condition of the roads and the financial implications for the municipalities as these assets change hands. He noted that the financial component of the project is the complicated piece that will need to be completed before any transfer can take place.